2026 Current Affairs practice question for Railways, SSC, UPSC. Review the correct answer and explanation, then continue with related practice below.
What is the capacity of the existing Dulhasti Stage-I Hydro Electric Project?
Correct Answerसही उत्तर
C. 390 MWC. 390 MW
Explanationव्याख्या
The existing Dulhasti Stage-I Hydro Electric Project has a capacity of 390 MW and has been operational since 2007 under NHPC Limited.
Dulhasti Stage-II, by contrast, is the proposed 260 MW extension.
Keeping the two capacities separate is important because they are easy to interchange in objective questions.
Existing Dulhasti Stage-I Hydro Electric Project की capacity 390 MW है और यह 2007 से NHPC Limited के अंतर्गत operational है। इसके विपरीत Dulhasti Stage-II proposed 260 MW extension है। परीक्षा में 390 MW और 260 MW को interchange करके confusing options दिए जा सकते हैं।
Practice More Like This
Vitorr selects questions using the same topic, subject, exam and overlapping concepts—not just database order.
Related Quizzes
Continue with quizzes connected to 2026 Current Affairs and Current Affairs. Sign up is required only when you start a quiz.