A project was planned for 180 days, but only 60% of days were productive due to rain. By what percentage must output per productive day increase to finish on time?
Correct Answerसही उत्तर
D. 66.67%D. 66.67%
Explanationव्याख्या
Detailed Step-by-Step Solution
Productive days = 180 × 0.60 = 108. If planned output was 1 unit/day, total work = 180 units. New required output = 180/108 = 5/3 units/day. Increase = (5/3 − 1) × 100 = 66⅔%. Shortcut: (100 − 60)/60 × 100 = 66⅔%.
Exam Insight & Verification
A reduction of available time to 60% requires productivity to become 100/60 = 5/3 times the original. This is an increase of 2/3, not 40%.
Correct answer: D — 66.67%
विस्तृत चरणबद्ध समाधान
उपलब्ध कार्यदिवस = 180 × 0.60 = 108। पहले प्रतिदिन 1 इकाई काम होता तो कुल 180 इकाई काम है। नई दर = 180/108 = 5/3 इकाई प्रतिदिन। वृद्धि = (5/3 − 1) × 100 = 66⅔%। संक्षिप्त विधि: 40/60 × 100 = 66⅔%।
परीक्षा उपयोगी तथ्य एवं जाँच
उपलब्ध कार्यदिवस 60% रह जाने पर दैनिक कार्यक्षमता मूल कार्यक्षमता की 100/60 = 5/3 गुना करनी होगी। वृद्धि 2/3 अर्थात 66.67% है, 40% नहीं।
सही उत्तर: D — 66.67%
Practice More Like This
Vitorr selects questions using the same topic, subject, exam and overlapping concepts—not just database order.
Related Quizzes
Continue with quizzes connected to Work and Time and Math. Sign up is required only when you start a quiz.